Summer wind conditions favor installation work in the Mutkalammi wind power area

In the Kalajoki and Kannus area, another 60-70 employees are working on commissioning the power plants, all 69 power plants in the area are now up and running. Heavy special transports have also arrived quickly and went better than expected. The wind turbines will be able to produce electricity with a power of 404 megawatts after the commissioning phase, during the rest of the year. When completed, the park will be Finland's largest onshore wind farm. Read here Suomen Yleisradio (YLE) news more about Mutkalamme's installation work!